OC15-005 – In the Matter of the Complaint Filed by Nebraska Public Power District, Chadron, Nebraska, Against Doug O’Bryan Contracting, Inc., Martin, South Dakota for an Incident Occurring on October 31, 2014,
at Two Miles East of Pine Ridge on Highway 18 North Side of Highway, Pine Ridge, S.D.
Date Filed: 01/22/15 ♦ Answer Deadline: 02/17/15 ♦ Docket Closed: 06/15/15
Agendas:
May 14, 2015, Corrected Agenda SD One Call Notification Board
March 27, 2015, Agenda of Enforcement Panel
Minutes:
May 14, 2015 (Draft Circulated 05/18/15)
March 27, 2015, Minutes of Enforcement Panel
Orders: Orders are in Adobe Acrobat *.pdf format
Filed Documents:
- 01/22/15 – Complaint
- 01/26/15 – Notice of Complaint, Deadline for Answer
- 02/17/15 – Doug O’Bryan Contracting, Inc.’s Response to Complaint
- 03/23/15 – South Dakota One Call Executive Director’s Email regarding South Dakota One Call Enforcement Panel Agenda of March 27, 2015
- 04/09/15 – South Dakota One Call Executive Director’s Letter regarding Enforcement Panel Recommendation
- 05/04/15 – Nebraska Public Power District’s Letter to Executive Director regarding Complaints OC15-001 and OC15-005
- 05/06/15 – South Dakota One Call Executive Director’s Email regarding SD One Call Notification Board Agenda of May 14, 2015
- 06/15/15 – Docket Closed