OC19-010 – In the Matter of the Complaint Filed by Watertown Municipal Utilities, Watertown, SD Against Schuelke Construction, Willow Lake, SD for an Incident Occurring on May 13, 2019 at 523 1st Ave NE, Watertown, SD
Date Filed: 05/24/19 ♦ Deadline to Respond June 19, 2019 ♦ Closed
Documents Filed:
- 5/24/19 – OC19-010 – Complaint
OC19-010 – Ticket No. 1913014796
OC19-010 – Images of Work Site - 5/29/19 – OC19-010 Notice of Complaint and Deadline to Respond
- 6/12/19 – OC19-010 – Schuelke Construction’s Response to Complaint
- 7/9/19 – OC19-010 – Panel Recommendations and Cover Letter
- 7/9/19 – OC19-10 – Panel Recommendation
- 08/28/19 – OC19-010 – Final Board Order
- 09/30/19 – Payment Received (Receipt Confidential)
- 04/24/20 – South Dakota One Call Deputy Director’s Letter Regarding Demand of Payment
- 05/07/20 – Schuelke attended a Damage Prevention Meeting through Zoom
- 05/07/20 – OC19-010 In House Safety Meeting
- 05/08/20 – Docket Closed