OC20 -025 – In the Matter of the Complaint Filed by Montana Dakota Utilities, Rapid City, SD against Underground Construction, Rapid City, SD, for an incident occurring on March 5, 2020 at 609 Franklin St, Rapid City, SD.
Date Filed: 04/29/2020 ♦ Deadline to Respond May 25, 2020 ♦ Pending
Documents Filed:
- 04/29/2020 – OC20-025 – Complaint
- 04/29/2020 – OC20-025 Notice of Complaint and Deadline to Respond
- 05/21/2020 – OC20-025 South Dakota One Call Enforcement Panel Meeting Email
- 06/18/2020 – OC20-025 – South Dakota One Call Enforcement Panel Meeting Email
- 08/04/2020 – OC20-025 Panel recommendations and cover letter
- 09/23/2020 – OC20-025 Signed Board Order
- 12/23/2020 – OC20-025 30 Day Demand for Payment
- 12/28/2020 – 30 Day Demand for Payment was returned via USPS.
- 12/28/2020 – OC20-025 30 Day Demand for Payment Remailed 12.28.2020.
- 01/04/2021 – OC20-025 In House Safety Meeting
- 01/29/2021 – Payment Received, $1,000. Receipt confidential.